Every UPS needs servicing, and eventually replacing, without shutting down the equipment it protects. Bypass paths make that possible: a static bypass inside the UPS that takes over automatically when the inverter cannot carry the load, and a maintenance bypass outside it that lets technicians isolate the whole unit. A UPS installed without a proper maintenance bypass turns every service visit into a planned outage.

The static bypass

Most online UPS units have an internal static bypass: a fast electronic switch that can connect the load directly to the incoming supply, skipping the rectifier and inverter. The UPS transfers to static bypass automatically when the inverter faults, when the load exceeds what the inverter can carry, or when a technician commands it. When conditions return to normal, it transfers back. For transfers to happen without a break, the inverter output must be in sync with the bypass supply, which the UPS manages continuously.

The static bypass keeps the load running through many UPS problems, but the load is then on raw supply with no battery backup. And the static bypass is inside the UPS, so it cannot be used to isolate the UPS for work.

The maintenance bypass

A maintenance bypass, sometimes called a wraparound bypass, is an external arrangement of breakers or switches that routes power around the entire UPS. With it closed and the UPS input and output opened, the UPS can be serviced, repaired or replaced while the load stays powered from the supply.

Supply utility or gen normal path input UPS rectifier, inverter output Load interlocked Maintenance bypass normally open
A three-breaker maintenance bypass. In normal operation the input and output breakers are closed and the load is fed through the UPS. For maintenance, the bypass breaker is closed and the UPS input and output are opened, so the load is fed directly from the supply while the UPS is isolated. Interlocks prevent the breakers being operated in an unsafe order.

The arrangement is usually built into a separate wall-mounted bypass cabinet or into the UPS switchgear, so that it stays in service while the UPS cabinet itself is removed. Interlocks, either mechanical key interlocks or electrical permissives from the UPS, stop the bypass from being closed while the UPS is out of sync with the supply, and stop the UPS from being reconnected in a way that would parallel two unsynchronized sources. For small plug-in units, external bypass power distribution units serve the same purpose.

Switching to maintenance bypass

The switching sequence depends on the UPS and the bypass design, and the manufacturer's procedure always governs. A typical sequence looks like this.

1 Plan and notify written procedure 2 UPS to static bypass load on supply 3 Close bypass interlock permits 4 Open output, input UPS isolated 5 Service, reverse back to inverter Steps 2 to 5 load has no battery backup
A typical transfer to maintenance bypass. The UPS is first placed on its static bypass, then the interlocked maintenance bypass is closed and the UPS output and input are opened. The red brackets mark the steps when the load runs on raw supply with no battery behind it, which is why the work is planned for a low-risk window. Always follow the manufacturer's procedure.

Three things make this go smoothly:

  • A written method of procedure that lists every switching step, who does it, what to check before the next step and how to back out if something unexpected happens.
  • Clear labels on every breaker and switch, matching the procedure and the single-line diagram posted at the equipment.
  • A low-risk window. While on bypass, a utility disturbance reaches the load directly. Schedule work when the business can tolerate that, confirm the generator is available, and tell the people who depend on the load.

Most dropped loads during UPS service are switching errors: a breaker opened in the wrong order, the wrong cabinet, or a bypass that was never wired the way the label says. A walk-through of the procedure at the equipment before the work day catches most of them.

A typical case

A regional office has a three-phase online UPS in its server room. The UPS is due for a capacitor and fan replacement, and the service company says the work will take most of a day. The installation drawings show a maintenance bypass, but nobody on site has used it.

Before booking the work, the facility manager asks for a walk-through. At the equipment, the electrician and the service technician find that the bypass cabinet labels do not match the single-line diagram, and that one breaker described as the output isolation breaker actually feeds a separate panel. The labels are corrected, the single-line diagram is updated and the method of procedure is rewritten to match what is really there.

On the day, the work is scheduled for a weekend, the generator is checked beforehand, the IT team is told when the load will be unprotected, and the switching follows the revised procedure step by step. The load stays up through the whole job. Without the walk-through, the first switching step would have opened the wrong breaker.

What UPS maintenance covers

UPS maintenance is normally done by the manufacturer's service organization or a qualified service company, following the manufacturer's schedule. The table shows what a program typically includes.

TaskTypical frequencyWhy
Check alarms, event log and display readingsCommonly weekly or monthly by site staffCatch warnings, transfers and battery alarms early
Preventive maintenance visitAs the manufacturer recommends, commonly yearly or twice yearlyClean, inspect, test transfers, check settings and firmware
Battery inspection and measurementsPer manufacturer, often at each visit or more oftenFind weak blocks before an outage does
Infrared scan of connectionsCommonly yearly, under loadFind loose or overheating connections
Replace fans and capacitorsAt the service life the manufacturer givesThese wear out and are a common cause of failures
Battery replacementEnd of service life or on test resultsRestore runtime before it is needed

For battery testing, see UPS batteries and runtime. For thermal scanning of UPS and distribution connections, see infrared thermography for electrical systems.

Qualified people only. UPS cabinets contain stored energy in batteries and capacitors that remains after the input is opened, and bypass switching is live work on energized equipment. Switching and service must only be done by trained, qualified people following the manufacturer's procedures, lockout requirements and arc flash precautions. See arc flash basics.

If your UPS has no maintenance bypass

Older installations and some small systems were installed without an external bypass. Every service visit then requires shutting down the load, and replacing the UPS means a longer outage still. Adding a bypass cabinet is often a worthwhile project in its own right, and it is usually done during a planned shutdown with the cabinet wired so that the next UPS replacement can happen with the load running. Check that the bypass is rated for the available fault current and coordinated with upstream protection.

How ehZee can help

We design bypass arrangements, interlocks and labelling into new UPS systems and add them to existing ones, as part of our UPS system design service. Drawings are sealed by a licensed professional engineer where required and installation is by licensed electrical contractors. We can also review an existing installation and its procedures for single points of failure.

Common questions

Why did our UPS go to bypass on its own?

Usually because of an overload, an inverter fault, overheating or a failed component. The event log shows the reason. Some units return automatically when the cause clears; others need a technician. Either way, the cause should be found.

Is the static bypass enough for maintenance?

No. The static bypass is inside the UPS, so the UPS cannot be fully isolated or removed while the load is on it. A maintenance bypass is needed for that.

Can our own staff do the bypass switching?

Only if they are trained and qualified for that equipment and procedure. Many owners leave switching to the UPS service technician, with site staff observing and following the method of procedure.

How long can the load safely stay on maintenance bypass?

There is no fixed limit, but every hour on bypass is an hour without protection from outages or disturbances. Plan the work so the time on bypass is as short as practical, have parts on site before switching, and return the load to the inverter as soon as the UPS has been tested.